Contract Agreement Amount

Rs. 45,57,347

Physical Progress

50.00%

Financial Progress

96.08%

Remaining Payment

Rs. 3

Construction of Black Topped Road at Birtabazar - Miyabari - Butabari Road (0-504-1+184), Jhapa

Office: डिभिजन सडक कार्यालय, झापा (13)

Fiscal Year: 076-77

50.00%

Contract Date: 8-Nov-19

Start Date: 8-Nov-19

Completion Date: 13-May-2020 (EOT Not Done)

Project Description

No description available.