Contract Agreement Amount
Rs. 24,35,79,878
Physical Progress
99.00%
Financial Progress
96.04%
Remaining Payment
Rs. 3
Dhading - Gorkha Road Project Section - 03
Office: आयोजना निर्देशनालय, ए.डि.वि., विशालनगर, काठमाण्डौ (77)
Fiscal Year: 073-74
Contract Date: 26-Apr-17
Start Date: 9-May-17
Completion Date: 30-Nov-2019 (EOT Done)
Project Description
No description available.