Contract Agreement Amount
Rs. 28,74,08,007
Physical Progress
94.93%
Financial Progress
96.03%
Remaining Payment
Rs. 3
Roadway Excavation & Improvement upto Gravel top Standard along Bahunepati-Dolalghat-Chaurikhola sector (ch78+117-89+968) Ramechhap District
Office: Puspalal (Midhill) Road Project, Kavrepalanchok (274)
Fiscal Year: 074-75
Contract Date: 23-Feb-18
Start Date: 23-Feb-18
Completion Date: 21-Aug-2020 (EOT Done)
Project Description
No description available.