Contract Agreement Amount

Rs. 2,18,22,866

Physical Progress

100.00%

Financial Progress

96.02%

Remaining Payment

Rs. 3

construction of RCC Bridge at kisne khola along gwaldubba-baigundhura road

Office: डिभिजन सडक कार्यालय, झापा (13)

Fiscal Year: 067-68

100.00%

Contract Date: 6-Apr-11

Start Date: 6-Apr-11

Completion Date: 05-Apr-2013 (EOT Not Done)

Project Description

No description available.