Contract Agreement Amount
Rs. 2,09,67,359
Physical Progress
0.00%
Financial Progress
0.00%
Remaining Payment
Rs. 100
Bhimad Rampur Mityal Aarungkhola Sadakko Bhimad Rampur Sadak NH-68 (Chainage 15+600 to 24+000), Tanahun
Office: सडक विभाग, काठमाण्डौ (2)
Fiscal Year: 080-81
Contract Date: 18-Oct-23
Start Date: 18-Oct-23
Completion Date: 29-Jun-2024 (EOT Not Done)
Project Description
No description available.