Contract Agreement Amount
Rs. 2,87,78,459
Physical Progress
96.00%
Financial Progress
96.00%
Remaining Payment
Rs. 4
Construction of 2 webbwd RCC slab Deck Over Dopai Khola Motorable Bridge, Chhiwang VDC Rukum
Office: डिभिजन सडक कार्यालय, चौरजहारी (181)
Fiscal Year: 074-75
Contract Date: 15-Jul-18
Start Date: 15-Jul-18
Completion Date: 28-Dec-2020 (EOT Done)
Project Description
No description available.