Contract Agreement Amount

Rs. 2,62,56,519

Physical Progress

0.00%

Financial Progress

95.97%

Remaining Payment

Rs. 4

Construction of Motorable Concrete Bridge over Siurung Khola along Besisahar Chame Road

Office: सडक डिभिजन, तनहुं (25)

Fiscal Year: 072-73

0.00%

Contract Date: 2-Oct-16

Start Date: 11-Nov-16

Completion Date: 29-Jan-2020 (EOT Done)