Contract Agreement Amount

Rs. 7,06,500

Physical Progress

96.00%

Financial Progress

95.96%

Remaining Payment

Rs. 4

Thermoplastic Painting & Enamel Painting works at different location of lalitpur District (Package-3)

Office: डिभिजन सडक कार्यालय, ललितपुर (23)

Fiscal Year: 076-77

96.00%

Contract Date: 8-Jun-20

Start Date: 8-Jun-20

Completion Date: 03-Aug-2020 (EOT Not Done)