Contract Agreement Amount
Rs. 51,31,944
Physical Progress
0.00%
Financial Progress
95.95%
Remaining Payment
Rs. 4
Godaita Tower Jhagadu Chowk Belhi Bajar Shripur Katani Murtiya Hariwon Sadak, Sarlahi
Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)
Fiscal Year: 076-77
Contract Date: 30-Dec-19
Start Date: 30-Dec-19
Completion Date: 01-Oct-2020 (EOT Done)
Project Description
No description available.