Contract Agreement Amount
Rs. 57,88,834
Physical Progress
100.00%
Financial Progress
95.92%
Remaining Payment
Rs. 4
Barahathwa-Samanpur-Katahariya-Santpur-Kalaiya Sadak at Santpur-Malahi Sector, Rautahat
Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)
Fiscal Year: 074-75
Contract Date: 26-Jun-18
Start Date: 26-Jun-18
Completion Date: 26-Nov-2019 (EOT Done)
Project Description
No description available.