Contract Agreement Amount

Rs. 7,84,49,595

Physical Progress

95.92%

Financial Progress

95.92%

Remaining Payment

Rs. 4

Gravelling Work,Masonry Drain & Structure,Cross Drainage Work in Rupakhet Kharigaira Gaidabaaz Road(Ch 0+000-8+000)Km,Dailekh. RDSKT/33701137-4/076/77-73

Office: सडक डिभिजन, सुर्खेत (33)

Fiscal Year: 076-77

95.92%

Contract Date: 18-Jun-20

Start Date: 18-Jun-20

Completion Date: 12-Feb-2021 (EOT Not Done)

Project Description

No description available.