Contract Agreement Amount
Rs. 1,14,68,932
Physical Progress
58.49%
Financial Progress
95.90%
Remaining Payment
Rs. 4
Upgrading and Rehabiliation of Road in Anarkholi-Khodpe-Patan Section of Pushpalal (Mid Hill) Highway (NH03)
Office: सडक डिभिजन, बैतडी (36)
Fiscal Year: 078-79
Contract Date: 29-Aug-21
Start Date: 29-Aug-21
Completion Date: 30-Dec-2021 (EOT Not Done)
Project Description
No description available.