Contract Agreement Amount
Rs. 56,60,200
Physical Progress
95.89%
Financial Progress
95.87%
Remaining Payment
Rs. 4
Reactive Maintenance works on Sanfe-Bayalpat aand Sanfe-Rakse Road Section
Office: Unknown (1)
Fiscal Year: 080-81
Contract Date: 24-Sep-23
Start Date: 24-Sep-23
Completion Date: 16-Dec-2023 (EOT Not Done)
Project Description
No description available.