Contract Agreement Amount

Rs. 40,85,156

Physical Progress

100.00%

Financial Progress

95.83%

Remaining Payment

Rs. 4

Construction of SaljhandiJarlewaBankasiyaDiyoDandaPragatichokChapalitoleRudrapurUccha Ma.bi SantinagarGaidahawataal Min Manawa Lumbini Road, Rupandehi and SainamainaNa.PaBasgadhi-KanchanGa.PaGajediLausaChaupari-Bakullaghat-RamapurLumbiniSadak, Rupandehi

Office: सडक डिभिजन, वुटवल (28)

Fiscal Year: 076-77

100.00%

Contract Date: 12-May-19

Start Date: 12-May-19

Completion Date: 30-Jun-2019 (EOT Not Done)

Project Description

No description available.