Contract Agreement Amount
Rs. 1,65,61,864
Physical Progress
0.00%
Financial Progress
95.81%
Remaining Payment
Rs. 4
MHWH/MWR/Bridge 068/069
Office: Puspalal (Midhill) Road Project, Dailekh (277)
Fiscal Year: 068-69
Contract Date: 28-May-12
Start Date: 12-Jun-12
Completion Date: 30-Jun-2020 (EOT Done)
Project Description
No description available.