Contract Agreement Amount
Rs. 15,04,919
Physical Progress
0.00%
Financial Progress
95.80%
Remaining Payment
Rs. 4
Drainage Works in Rampur Nagarpalika 5 (Tal Pokhara - Khutte Gara - Bijayapur - Bejad Road), Palpa
Office: सडक डिभिजन, पाल्पा (27)
Fiscal Year: 076-77
Contract Date: 1-Jan-70
Start Date: 11-Jun-20
Completion Date: 11-Jan-2021 (EOT Done)
Project Description
No description available.