Contract Agreement Amount

Rs. 51,03,389

Physical Progress

95.75%

Financial Progress

95.75%

Remaining Payment

Rs. 4

Rehabilititaion Works on Surkhet-Dailekh Road(Ch:61+400 to 63+500 and 67+000 to 68+000),Dailekh

Office: सडक डिभिजन, कपिलवस्तु (29)

Fiscal Year: 079-80

95.75%

Contract Date: 27-Apr-23

Start Date: 27-Apr-23

Completion Date: 30-Jun-2023 (EOT Not Done)

Project Description

No description available.