Contract Agreement Amount

Rs. 1,00,36,833

Physical Progress

100.00%

Financial Progress

95.74%

Remaining Payment

Rs. 4

Road Upgrading Works on Changunarayan Dhurtamarga(Fast Track) Bhaktapur

Office: सडक डिभिजन, भक्तपुर (24)

Fiscal Year: 076-77

100.00%

Contract Date: 29-Jun-20

Start Date: 29-Jun-20

Completion Date: 16-Oct-2020 (EOT Not Done)

Project Description

No description available.