Contract Agreement Amount

Rs. 4,24,19,138

Physical Progress

0.00%

Financial Progress

0.00%

Remaining Payment

Rs. 100

Periodic Maintenance Works along Galchhi-Trishuli Bridge section of PRM,Dhading

Office: डिभिजन सडक कार्यालय, चितवन (20)

Fiscal Year: 076-77

0.00%

Contract Date: 10-Jul-20

Start Date: 10-Jul-20

Completion Date: 30-Nov-2020 (EOT Not Done)

Project Description

No description available.