Contract Agreement Amount
Rs. 19,18,237
Physical Progress
0.00%
Financial Progress
95.72%
Remaining Payment
Rs. 4
Road Improvement Works at Hariwon-9 M.R.M. Bishnupur Purano Bazar Ganesh Chok Tivre Sadak, Sarlahi
Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)
Fiscal Year: 077-78
Contract Date: 26-Nov-20
Start Date: 29-Nov-20
Completion Date: 23-Mar-2021 (EOT Not Done)
Project Description
No description available.