Contract Agreement Amount

Rs. 10,97,39,778

Physical Progress

98.90%

Financial Progress

95.69%

Remaining Payment

Rs. 4

Design and Build of Bridge over Kada Khola, Seti Rajmarga (Kailali Doti-Achham), Kailali

Office: पच्चिमाञ्चल क्षेत्रिय सडक निर्देशनालय, पोखरा (9)

Fiscal Year: 078-79

98.90%

Contract Date: 13-Jul-22

Start Date: 13-Jul-22

Completion Date: 29-Mar-2025 (EOT Not Done)

Project Description

No description available.