Contract Agreement Amount
Rs. 1,77,33,859
Physical Progress
100.00%
Financial Progress
95.66%
Remaining Payment
Rs. 4
Rehabilitation (Black top,Drain & Miscellaneous work) along Silgadhi-Chaukhutte Road.
Office: सडक डिभिजन, डोटी (35)
Fiscal Year: 073-74
Contract Date: 2-Jul-17
Start Date: 2-Jul-17
Completion Date: 14-Jul-2018 (EOT Done)
Project Description
No description available.