Contract Agreement Amount
Rs. 11,54,080
Physical Progress
100.00%
Financial Progress
95.60%
Remaining Payment
Rs. 4
Road Widening and upgrading of Indreni Puwa sadak , changunarayan
Office: सडक डिभिजन, भक्तपुर (24)
Fiscal Year: 077-78
Contract Date: 12-Nov-20
Start Date: 12-Nov-20
Completion Date: 25-Feb-2021 (EOT Not Done)
Project Description
No description available.