Contract Agreement Amount

Rs. 72,09,389

Physical Progress

100.00%

Financial Progress

95.57%

Remaining Payment

Rs. 4

Upgrading and Improvement works on Bhalubang-Nuwakot-Khandah-Kharbang Road (Bhederakhane deurali-Gupha-Khan-Dhungare Section) Arghakhanchi

Office: सडक डिभिजन, कपिलवस्तु (29)

Fiscal Year: 078-79

100.00%

Contract Date: 2-Dec-21

Start Date: 2-Dec-21

Completion Date: 31-May-2022 (EOT Not Done)

Project Description

No description available.