Contract Agreement Amount
Rs. 2,91,20,631
Physical Progress
0.00%
Financial Progress
95.54%
Remaining Payment
Rs. 4
Maintenance works including earthworks, drainage, structural works and stone soling works
Office: उत्तर दक्षिण, कोशी सडक योजना, संखुवासभा (57)
Fiscal Year: 075-76
Contract Date: 27-Mar-19
Start Date: 1-Apr-19
Completion Date: 05-Jul-2019 (EOT Not Done)
Project Description
No description available.