Contract Agreement Amount

Rs. 41,11,55,901

Physical Progress

100.00%

Financial Progress

95.54%

Remaining Payment

Rs. 4

upgrading of tamagadhi simraungadh road bara 073.74UR019ch0+000-20+000

Office: हुलाकी राजमार्ग निर्देशनालय​, काठमाण्डौ (230)

Fiscal Year: 073-74

100.00%

Contract Date: 18-Jun-17

Start Date: 3-Jul-17

Completion Date: 18-Oct-2019 (EOT Done)