Contract Agreement Amount
Rs. 20,67,615
Physical Progress
0.00%
Financial Progress
95.51%
Remaining Payment
Rs. 4
Hariharpur Katani Maira Sadak, Rautahat
Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)
Fiscal Year: 076-77
Contract Date: 9-Feb-20
Start Date: 9-Feb-20
Completion Date: 11-Nov-2020 (EOT Done)
Project Description
No description available.