Contract Agreement Amount
Rs. 56,14,323
Physical Progress
95.00%
Financial Progress
95.40%
Remaining Payment
Rs. 4
Rehabilitation of Tarkeshwor na.pa. Astanarayan Hall Nepaltar Sheshmati Kavresthali badrinarayan dham Kavresthali tokha Sapantirtha Jhormahadev Budhanilkantha Shantidham Road
Office: डिभिजन सडक कार्यालय, काठमाण्डौ (22)
Fiscal Year: 076-77
Contract Date: 14-Nov-19
Start Date: 14-Nov-19
Completion Date: 14-Nov-2019 (EOT Not Done)
Project Description
No description available.