Contract Agreement Amount

Rs. 56,14,323

Physical Progress

95.00%

Financial Progress

95.40%

Remaining Payment

Rs. 4

Rehabilitation of Tarkeshwor na.pa. Astanarayan Hall Nepaltar Sheshmati Kavresthali badrinarayan dham Kavresthali tokha Sapantirtha Jhormahadev Budhanilkantha Shantidham Road

Office: डिभिजन सडक कार्यालय, काठमाण्डौ (22)

Fiscal Year: 076-77

95.00%

Contract Date: 14-Nov-19

Start Date: 14-Nov-19

Completion Date: 14-Nov-2019 (EOT Not Done)

Project Description

No description available.