Contract Agreement Amount

Rs. 5,20,11,193

Physical Progress

98.00%

Financial Progress

95.40%

Remaining Payment

Rs. 4

Construction of RCC Bridge over Sutiya Nadi near Chinimil on Belauri Na.Pa. 13, Kanchanpur

Office: सडक डिभिजन, कञ्चनपुर (34)

Fiscal Year: 073-74

98.00%

Contract Date: 21-May-17

Start Date: 21-May-17

Completion Date: 13-Jul-2021 (EOT Done)

Project Description

No description available.