Contract Agreement Amount
Rs. 5,20,11,193
Physical Progress
98.00%
Financial Progress
95.40%
Remaining Payment
Rs. 4
Construction of RCC Bridge over Sutiya Nadi near Chinimil on Belauri Na.Pa. 13, Kanchanpur
Office: सडक डिभिजन, कञ्चनपुर (34)
Fiscal Year: 073-74
Contract Date: 21-May-17
Start Date: 21-May-17
Completion Date: 13-Jul-2021 (EOT Done)