Contract Agreement Amount

Rs. 95,00,799

Physical Progress

96.00%

Financial Progress

95.36%

Remaining Payment

Rs. 4

Reactive Maintenance Works on Dumre Besisahar Road [Ch 9+500 - 12+000], Tanahun

Office: डुम्रे बेसीशहर चामे सडक योजना, बेसीशहर लमजुङ (299)

Fiscal Year: 078-79

96.00%

Contract Date: 4-Feb-22

Start Date: 4-Feb-22

Completion Date: 08-Oct-2022 (EOT Done)

Project Description

No description available.