Contract Agreement Amount
Rs. 19,03,625
Physical Progress
0.00%
Financial Progress
95.33%
Remaining Payment
Rs. 4
Road Upgrading works along Dhadkharka Bhanjyang Kartike Deurali Maadankudari Road Section
Office: सडक डिभिजन, भक्तपुर (24)
Fiscal Year: 076-77
Contract Date: 19-Mar-20
Start Date: 19-Mar-20
Completion Date: 22-Aug-2020 (EOT Not Done)
Project Description
No description available.