Contract Agreement Amount

Rs. 88,52,712

Physical Progress

0.00%

Financial Progress

95.32%

Remaining Payment

Rs. 4

Name of the Work : Road Way Upgrading,Excavation & Structure Works along Dethala-Khar-Khalanga Road,Darchula. (Ch.17+000 Km-19+000 Km)

Office: सडक डिभिजन, बैतडी (36)

Fiscal Year: 076-77

0.00%

Contract Date: 18-Jun-20

Start Date: 18-Jun-20

Completion Date: 04-Jan-2021 (EOT Done)

Project Description

No description available.