Contract Agreement Amount

Rs. 9,48,120

Physical Progress

0.00%

Financial Progress

95.30%

Remaining Payment

Rs. 4

Reactive Maintenance Works on Vyaas Marga (Chainage No. 0+000 to 29+100)

Office: सडक डिभिजन, तनहुं (25)

Fiscal Year: 076-77

0.00%

Contract Date: 6-Mar-20

Start Date: 6-Mar-20

Completion Date: 05-Jun-2020 (EOT Not Done)

Project Description

No description available.