Contract Agreement Amount

Rs. 38,76,650

Physical Progress

95.28%

Financial Progress

95.29%

Remaining Payment

Rs. 4

Roadway Improvement works on Rakam Pilka deuli Kaphalkot khaneta sima Thala Raikar Jajarkot Road Surkhet

Office: सडक डिभिजन, सुर्खेत (33)

Fiscal Year: 078-79

95.28%

Contract Date: 13-Aug-21

Start Date: 13-Aug-21

Completion Date: 15-Nov-2021 (EOT Not Done)