Contract Agreement Amount
Rs. 50,23,002
Physical Progress
100.00%
Financial Progress
95.26%
Remaining Payment
Rs. 4
Road Upgrading Works on Nagarkot Gauribisauna dhatkhola Road,Kavrepalanchowk
Office: सडक डिभिजन, भक्तपुर (24)
Fiscal Year: 076-77
Contract Date: 15-Dec-19
Start Date: 15-Dec-19
Completion Date: 08-Mar-2020 (EOT Not Done)