Contract Agreement Amount
Rs. 2,58,07,034
Physical Progress
95.19%
Financial Progress
95.24%
Remaining Payment
Rs. 4
Road Rehabilitation works on Sanfe-Balde-Martadi Road Section (CH. 00+000~57+000)
Office: डिभिजन सडक कार्यालय, साँफेवगर, अछाम (178)
Fiscal Year: 078-79
Contract Date: 21-Jan-22
Start Date: 21-Jan-22
Completion Date: 14-Jan-2023 (EOT Done)
Project Description
No description available.