Contract Agreement Amount

Rs. 95,55,038

Physical Progress

0.00%

Financial Progress

95.22%

Remaining Payment

Rs. 4

Construction of Approach Road, Side Drain and River Training woks at Amlekhgunj3 No. Bridge, Bara Fiscal Year : 2076/77 Project Start Fiscal Year : 2075/76 Project Completion Fiscal Year : 2075/76

Office: डिभिजन सडक कार्यालय, मकवानपुर (19)

Fiscal Year: 075-76

0.00%

Contract Date: 22-Apr-19

Start Date: 22-Apr-19

Completion Date: 05-Jul-2019 (EOT Not Done)

Project Description

No description available.