Contract Agreement Amount

Rs. 44,46,384

Physical Progress

95.00%

Financial Progress

95.22%

Remaining Payment

Rs. 4

21 Kilo Lisankhu Bafal Thokarpa Sukate Sadak, Sindhupalchok

Office: डिभिजन सडक कार्यालय, दोलखा (18)

Fiscal Year: 075-76

95.00%

Contract Date: 22-Apr-19

Start Date: 22-Apr-19

Completion Date: 10-Jul-2019 (EOT Not Done)

Project Description

No description available.