Contract Agreement Amount
Rs. 2,27,57,412
Physical Progress
95.00%
Financial Progress
95.20%
Remaining Payment
Rs. 4
Pavement Work including Cross Drainage and retaining Structures along Girija Prasad Koirala Marg Larikatta Gobindapur Dhadra Malamighat, Morang
Office: डिभिजन सडक कार्यालय, मोरङ (14)
Fiscal Year: 078-79
Contract Date: 30-Jan-22
Start Date: 30-Jan-22
Completion Date: 14-Jul-2022 (EOT Done)
Project Description
No description available.