Contract Agreement Amount

Rs. 2,27,57,412

Physical Progress

95.00%

Financial Progress

95.20%

Remaining Payment

Rs. 4

Pavement Work including Cross Drainage and retaining Structures along Girija Prasad Koirala Marg Larikatta Gobindapur Dhadra Malamighat, Morang

Office: डिभिजन सडक कार्यालय, मोरङ (14)

Fiscal Year: 078-79

95.00%

Contract Date: 30-Jan-22

Start Date: 30-Jan-22

Completion Date: 14-Jul-2022 (EOT Done)

Project Description

No description available.