Contract Agreement Amount

Rs. 49,42,946

Physical Progress

95.00%

Financial Progress

95.19%

Remaining Payment

Rs. 4

Rehabilitation work of SRN road along Ganahakhola-Chackchake Darbot Road ( Rolpa Border to Liwang Darbot Section Ch 27+000 to 63+000) Rolpa

Office: Road Division, Pyuthaan (258)

Fiscal Year: 077-78

95.00%

Contract Date: 18-Mar-21

Start Date: 18-Mar-21

Completion Date: 13-Jun-2021 (EOT Not Done)

Project Description

No description available.