Contract Agreement Amount
Rs. 23,84,180
Physical Progress
100.00%
Financial Progress
95.17%
Remaining Payment
Rs. 4
Road Construction Works along Koniya gaun to Chorni section of Birgunj 31 Prasotipur Koniya gaun Chorni, Laxmipur Parsawa Solakpur Ramban road, Parsa
Office: योजना तथा अनुगमन महाशाखा (HMIS तथा ICT शाखा) (6)
Fiscal Year: 079-80
Contract Date: 22-Nov-22
Start Date: 22-Nov-22
Completion Date: 13-Jun-2023 (EOT Not Done)
Project Description
No description available.