Contract Agreement Amount
Rs. 8,18,54,715
Physical Progress
0.00%
Financial Progress
95.13%
Remaining Payment
Rs. 4
Major Maintenance and Safety work of SRN Bridge along Mahendra Rajmarga from Budhikhola Bridge to Mawa Khola Bridge
Office: डिभिजन सडक कार्यालय, मोरङ (14)
Fiscal Year: 077-78
Contract Date: 5-Jul-21
Start Date: 5-Jul-21
Completion Date: 01-Jul-2022 (EOT Done)
Project Description
No description available.