Contract Agreement Amount
Rs. 12,28,84,285
Physical Progress
0.00%
Financial Progress
95.11%
Remaining Payment
Rs. 4
Construction of Steel Truss bridge over Karnali River, Khulalu, Kalikot
Office: डिभिजन सडक कार्यालय, जुम्ला (179)
Fiscal Year: 068-69
Contract Date: 12-Jul-12
Start Date: 12-Jul-12
Completion Date: 12-Feb-2021 (EOT Done)
Project Description
No description available.