Contract Agreement Amount

Rs. 14,24,347

Physical Progress

0.00%

Financial Progress

0.00%

Remaining Payment

Rs. 100

Patch Work (Recurrent Maintenance) at Sindhuligadhi -Nepalthok Road Section

Office: सूर्यविनायक-धुलिखेल​, धुलिखेल-सिन्धुली-बर्दिवास सडक आयोजना, काठमाण्डौ (225)

Fiscal Year: 075-76

0.00%

Contract Date: 28-Aug-18

Start Date: 28-Aug-18

Completion Date: 28-Nov-2018 (EOT Not Done)

Project Description

No description available.