Contract Agreement Amount
Rs. 8,04,69,967
Physical Progress
95.00%
Financial Progress
95.08%
Remaining Payment
Rs. 4
Rehabilitation works along Ghumti-Futbang (Ch 54+500 - 63+000) Section of Gorusinge-Sandhikharka NH51 Road
Office: डिभिजन सडक कार्यालय, ललितपुर (23)
Fiscal Year: 079-80
Contract Date: 8-May-23
Start Date: 8-May-23
Completion Date: 06-May-2024 (EOT Not Done)
Project Description
No description available.