Contract Agreement Amount

Rs. 1,16,91,632

Physical Progress

96.00%

Financial Progress

95.07%

Remaining Payment

Rs. 4

MAINTENANCE WORK ON RATNARAJMARGE(CH68+700-80+000)

Office: सडक डिभिजन, सुर्खेत (33)

Fiscal Year: 076-77

96.00%

Contract Date: 20-Jan-20

Start Date: 20-Jan-20

Completion Date: 03-Jul-2021 (EOT Done)

Project Description

No description available.