Contract Agreement Amount

Rs. 37,11,000

Physical Progress

100.00%

Financial Progress

95.06%

Remaining Payment

Rs. 4

Recurent Maintenance of East West Highway, Ch 981+000 - Ch 1018+410, Kanchanpur

Office: सडक डिभिजन, कञ्चनपुर (34)

Fiscal Year: 076-77

100.00%

Contract Date: 21-Jun-20

Start Date: 28-Jun-20

Completion Date: 28-Mar-2021 (EOT Not Done)

Project Description

No description available.