Contract Agreement Amount

Rs. 12,74,410

Physical Progress

100.00%

Financial Progress

95.05%

Remaining Payment

Rs. 4

Specific Maintenance works in Seti Highway

Office: सडक डिभिजन, डोटी (35)

Fiscal Year: 076-77

100.00%

Contract Date: 8-Jun-20

Start Date: 8-Jun-20

Completion Date: 08-Jan-2021 (EOT Done)

Project Description

No description available.