Contract Agreement Amount

Rs. 2,22,58,240

Physical Progress

100.00%

Financial Progress

95.01%

Remaining Payment

Rs. 4

Periodic Maintenance of Mahakali Highway NH 66 {Ghumti(Budar) Gaira Section} Chainage 67+400~82+000

Office: सडक डिभिजन, डोटी (35)

Fiscal Year: 077-78

100.00%

Contract Date: 16-Feb-21

Start Date: 22-Feb-21

Completion Date: 04-Jul-2021 (EOT Not Done)

Project Description

No description available.