Contract Agreement Amount
Rs. 67,84,468
Physical Progress
100.00%
Financial Progress
94.91%
Remaining Payment
Rs. 5
Roadway Improvement Works along Krishnanagar Na.Pa. Wada No. 11 Finda Dekhi Bijayanagar Ga.Pa. Wada No. 4 Tripalnagar Samma Bato 10 km Road and Bijayanagar Gaupalika 6 dekhi Shivraj Nagarpalika Sadak Kapilvastu
Office: पुर्वाञ्चल क्षेत्रिय सडक निर्देशनालय, झापा (7)
Fiscal Year: 079-80
Contract Date: 18-Sep-22
Start Date: 18-Sep-22
Completion Date: 30-May-2023 (EOT Done)
Project Description
No description available.